The development of four photovoltaic power plants has commenced at the start of April 2011, this time in the areas Mokrá Lúka and Horovce, Slovakia. New solar power plants will take up an area of 8.6 ha and a total of 18 090 highly effective PhonoSolar PS190M-24F panels we used in their development.
These panels are manufactured from durable materials and undergo a very strict inspection. Complete development of all complexes is provided by our EPC partner Efektim, a.s.
The solar power plant development schedule
The construction of the complexes will take about three months, because the completion and commissioning of the power plants is scheduled for June 2011. AC cabling and grounding are currently installed on the technically ready lot, along with fencing and support structures, which are now being fitted with PhonoSolar PS190M-24F photovoltaic panels. FVE Horovce 1 and FVE Horovce 2 are being constructed in the Horovce municipality. The output generated by these solar power plans will reach 84 960 Wp and 492 480 Wp. Investors of these complexes are FVE Horovce 1 s. r. o. and FVE Horovce 2 s. r. o.
At the same time there is also an ongoing development of FVE Kresandra and FVE Power Plant near the Mokrá Lúka municipality. The output generated by these power plants will reach 984.96 kWp and 974.70 kWp and their investors are Kresandra s.r.o. and FV Power Plant s. r. o.
PhonoSolar Photovoltaic panels
First grade materials that ensure long life span, durability and 100% performance are used in the production of PhonoSolar panels. Thanks to their high quality PhonoSolar panels are used in the developments of small and large scale photovoltaic power plants around the world. As an example we can state the largest photovoltaic power in the Czech Republic – FVE Vepřek – where a total of 186 960 PhonoSolar panels were installed.